2012 saskatoon roadway and sidewalk project
Construction is scheduled to commence on April 30th for the hard surface work in the parking lot west of the SED Systems building, Innovation Boulevard and Perimeter Road.
Stage One construction is expected to start at the end of April, and should be complete by the end of June. This work will entail all of the work within the parking lot, roundabout and extension that can be completed without closing Perimeter Road. This will also include the closing of the road directly east of 421 Downey Road.
Stage Two will start as soon as Stage One is complete. This work will consist of tie-ins to Perimeter Road and related U of S connections. It is anticipated that this work will be completed by the end of July. For the majority of this time Perimeter Road will be closed.
We are also working with Transit Services to re-route the buses during this time. Additional information to follow.
As construction proceeds we will continue to provide regular updates.
For everyone's safety and comfort we ask that you avoid the work areas mentioned below while the work is in progress. Please contact our office at saskatoon@innovationplace.com or 306.933.6609 if you have any questions.
We apologize for any inconvenience this construction may cause. Thank you for your patience and cooperation. |